Remodel front office to improve security & privacy, completed Summer, 2012 
Repair and add outdoor pole lights as needed, completed Summer 2012    
Replace wall pack unit in portables - Replace A/C units with 3-ton
Replace exterior door frames and hardware in kitchen completed Summer, 2012
Expand front & back parking lots.  completed Summer, 2011
Replace kitchen air handling units and controls
Replace secondary chilled water pump
Replace (12) exhaust fans, completed Summer 2012
Replace (2) sets of doors in cafeteria, completed Summer, 2012
T-building repair, includes ramps and power washing completed Summer, 2010
Replace kitchen floor with quarry tile scheduled Summer, 2013
Replace kitchen walk-in assembly with new 216 sq. ft. with shelving